Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Time (weeks) Probability 0.31 0.31 0.29 0.09 Activity 0.18 0.58 0.24 8 15 17 19 21 23 10 12 0.10 0.24 0.35 0.21 0.10 0.64 0.36Explanation / Answer
Activity Time
Cumulative
Random Number interval
Activity
(weeks)
Probability
A
6
0.31
0.31
0.00 but less than 0.31
7
0.31
0.62
0.31 but less than 0.62
8
0.29
0.91
0.62 but less than 0.91
9
0.09
1
0.91 but less than 1
B
5
0.18
0.18
0.00 but less than 0.18
7
0.58
0.76
0.18 but less than 0.76
9
0.24
1
0.76 but less than 1
C
15
0.10
0.10
0.00 but less than 0.1
17
0.24
0.34
0.10 but less than 0.34
19
0.35
0.69
0.34 but less than 0.69
21
0.21
0.9
0.69 but less than 0.9
23
0.10
1
0.9 but less than 1
D
10
0.64
0.64
0.00 but less than 0.64
12
0.36
1
0.68 but less than 1
Activity
Random Number
Completion Time
A
0.7089
8 weeks {0.62 < 0.7089 < 0.91
B
0.9241
9 weeks {0.76 <0.241 <1}
C
0.4401
19 weeks { 0.34 <0.4401 <0.69
D
0.2105
10 weeks (0.2105 <0.64)
Total
46 weeks
Please rate my solution
Activity Time
Cumulative
Random Number interval
Activity
(weeks)
Probability
A
6
0.31
0.31
0.00 but less than 0.31
7
0.31
0.62
0.31 but less than 0.62
8
0.29
0.91
0.62 but less than 0.91
9
0.09
1
0.91 but less than 1
B
5
0.18
0.18
0.00 but less than 0.18
7
0.58
0.76
0.18 but less than 0.76
9
0.24
1
0.76 but less than 1
C
15
0.10
0.10
0.00 but less than 0.1
17
0.24
0.34
0.10 but less than 0.34
19
0.35
0.69
0.34 but less than 0.69
21
0.21
0.9
0.69 but less than 0.9
23
0.10
1
0.9 but less than 1
D
10
0.64
0.64
0.00 but less than 0.64
12
0.36
1
0.68 but less than 1