Please thoroughly answer all parts of this question 34. Consider the following p
ID: 329541 • Letter: P
Question
Please thoroughly answer all parts of this question
34. Consider the following product structure diagram, representing a bill of materials required to assemble some finished good A: 0090 (Items A through FF have been sketched as circles for convenience, but represent the same information as a product structure diagram sketched with squares, or any other shapes.) Please answer the following questions, based on this information a. Who is the parent of item N? b. Who are the children of item B? c. List all raw material items. d. Item S belongs to what level? e. Suppose you have absolutely no inventory on hand, but you want to assemble one unit of finished good A. The lead time associated with each and every item pictured in the product structure is exactly 1 week. How long would it take you to complete the one unit of A?Explanation / Answer
a. F is the parent of item N, which in turn is child of A.
b. I and J are the children of B
c. Materials Y, Z, AA,BB,CC,DD,EE and FF, which are at the last level of product structure diagram are raw materials.
d. Item S belongs to the level 3.
e. If the work starts from the beginning of week 1, by the end of week 1, level 4 components will be ready. Similarly level 3 will be ready by the end of week 2, level 2 by the end of week 3, Level 1 by the end of week 4, and the finished product will be ready by the end of week 5.