Courtney Kamauf schedules labor for the production of a popular Rustic Coffee Ta
ID: 331054 • Letter: C
Question
Courtney Kamauf schedules labor for the production of a popular Rustic Coffee Table at Kamauf Enterprises, Inc. The table requires a top, four legs 4 galon of stain. g gallon of glue, 2 short braces between the legs and 2 long braces between the legs, and a brass cap that goes on the bottom of each leg. Lead time is 1 day for each item. Schedule the order releases necessary to produce 656 coffee tables on days 5 and 6, and 1 and 8. The labor standard for each top is 2 labor hours, each leg including brass cap installation requires 7 hour, as does each pair of braces Base assembly requires 1 labor-hour, and final assembly requires 2 labor-hours. What is the total number of labor hours required each day, and how many employees are needed each day at 8 hours per day? COFFEE TABLE Top Stainue Base Assembly Short Long Legs braces braces Brass and determine the total number of labor-hours required each day and the number of employees needed Construct the coffee table master schedule each day (enter your responses as whole numbers) Cofec Tabio MasterHead Day 1 Day2 Day3 Day 4 Days Day 6 Day 7 Day a ay Dby2 buy) Day Doy Schedule Required Time Gross Requirements Table Assembly Top Preparation Assemble Base Long Brace (2) Short Brace (2) Leg Preparation (4) 0.50 Total Hours Employees need 0.501 0.501 1 Enter your answer in each of the answer boxes
Explanation / Answer
The Master schedule is as follows:
Coffee Table Master Schedule
Hrs. Req.
Lead Time
Day 1
Day 2
Day 3
Day 4
Day 5
Day 6
Day 7
Day 8
Gross Req.
656
656
136
136
Table Assembly
2
1
656
656
136
136
Top Preparation
2
1
656
656
136
136
Assemble Base
1
1
656
656
136
136
Long Brace (2)
0.5
1
2*656
= 1312
1312
272
272
Short Brace (2)
0.5
1
2*656
= 1312
1312
272
272
Leg Preparation (4)
0.5
1
4*656
= 2624
2624
544
544
Total Hours
2624
4592
3824
2264
680
272
0
Employees need
2624/8
= 328
574
478
283
85
34
Coffee Table Master Schedule
Hrs. Req.
Lead Time
Day 1
Day 2
Day 3
Day 4
Day 5
Day 6
Day 7
Day 8
Gross Req.
656
656
136
136
Table Assembly
2
1
656
656
136
136
Top Preparation
2
1
656
656
136
136
Assemble Base
1
1
656
656
136
136
Long Brace (2)
0.5
1
2*656
= 1312
1312
272
272
Short Brace (2)
0.5
1
2*656
= 1312
1312
272
272
Leg Preparation (4)
0.5
1
4*656
= 2624
2624
544
544
Total Hours
2624
4592
3824
2264
680
272
0
Employees need
2624/8
= 328
574
478
283
85
34