Match the term with the definition.
Activities that must be completed prior to initiation of a later activity in the network.
Activities that cannot be started until previous activities have been completed.
The path through the project network with the longest duration.
A network analysis technique used to determine which path has the least amount of scheduling flexibility and will most likely determine when a project can be completed.
An event- and probability-based network analysis system generally used in projects where activities and their durations are difficult to define.
1. Predecessor
2. Successor
3. Critical path
4. Critical path method(CPM)
5. Program Evaluation & Review Technique(PERT)
Explanation / Answer
Match the term with the definition.
Activities that must be completed prior to initiation of a later activity in the network.
Activities that cannot be started until previous activities have been completed.
The path through the project network with the longest duration.
A network analysis technique used to determine which path has the least amount of scheduling flexibility and will most likely determine when a project can be completed.
An event- and probability-based network analysis system generally used in projects where activities and their durations are difficult to define.
1. Predecessor
2. Successor
3. Critical path
4. Critical path method(CPM)
5. Program Evaluation & Review Technique(PERT)