The following Level 0 MRP information is given for a personal computing system.

ID: 348468 • Letter: T

Question

The following Level 0 MRP information is given for a personal computing system. Monitors for these computing systems are a Level 1 item and each computer receives only one monitor Using a lead time of one week, what are the Level 1 Gross Requirements for Monitors? Assume any inventory on hand will be used as soon a possible Week MRP Level 0: Computing System 1100 200 500 600 300 100 200 600 Gross Requirements 400 600 200 500 Planned Order Releases A.1100 in week 3, 600 in week 4, 300 in week 5 B. 1100 in week 2, 600 in week 3, 300 in week 4 C.500 in week 1, 600 in week 2, 200 in week 3 D.500 in week 2, 600 in week 3, 200 in week 4 E. Impossible to determine from this information

Explanation / Answer

In the level 0 MRP, monitors for the computing systems are level 1and each computer recieves one monitor if we use a lead time of one week, the level 1 gross requirements for monitors are

B. 1100 in week 2, 600 in week 3, 300 in week 4