Following data were obtained by a work study. (i) Maintenance time (a) Get out a

ID: 350650 • Letter: F

Question

Following data were obtained by a work study.

(i) Maintenance time

(a) Get out and put away tools = 12.0 min/day

(b) Cleaning of machine = 5.0 min/day

(c) Oiling of machine = 5.0 min/day

(d) Replenish coolant supply = 3.0 min/day

(ii) Interruption

(a) Interruption by foreman = 5.0 min/day

(b) Interruption by porter etc. = 4.0 min/day

(iii) Delay time due to power failure etc. = 6.0 min/day

(iv) Personal time = 20.0 min/day

Calculate total allowances, total available cycle time productive hours, considering a working

day of 8 hours.

Explanation / Answer

To be calculated:

(a) Total allowances

(b) Total available cycle time

(c) Total productive hours

Solution:

(a) Total allowance is calculated as;

Total allowance = (Total Maintenance time + Total Interruption + Delay time + Personal time)

Total allowance = (12.0 + 5.0 + 5.0 + 3.0) + (5.0 + 4.0) + 6.0 + 20.0

Total allowance = 60 minutes per day

(b) Total available cycle time is calculated as;

Total available cycle time = Total hours in a working day - Total allowances

Total working hours = 8 hours = 480 minutes

Total available cycle time = 480 - 60 = 420

Total available cycle time = 420 minutes per day

(c) Number of productive hours is calculated as;

Productive hours = Available cycle time / 60 (1 hour = 60 minutes)

Productive hours = 420 / 60

Productive hours = 7

Number of productive hours = 7 hours