Formal shop-floor control systems are necessary under JIT? a. True b. False 2. T
ID: 357353 • Letter: F
Question
Formal shop-floor control systems are necessary under JIT?
a. True b. False
2. The objective of Theory of Constraints (TOC) is to maximize the utilization of both bottleneck and non-bottleneck resources.
a. True b. False
3. In TOC scheduling, buffers are normally maintained before and after bottleneck resources?
a. True b. False
4. In the one-machine case, the order of job processing is not an important factor in performance?
a. True b. False
5. The shortest processing time (SPT) sequencing rule performs well to minimize the average number of jobs in the system.
a. True b. False
Explanation / Answer
1 False
The above statement is false. Formal shop-floor control systems are unnecessary in Just in Time.
2 False
The objective is to maximize throughput.
3 True
In TOC scheduling, buffers are normally maintained before and after bottleneck resources
4 False
The above statement is false