AT&T; 4G 6:17 PM moodle.selu.edu 10. All times are in weeks. Answer the following questions: a) What is the impact on the end date of the project if activity I slips by three weeks? b) By how many weeks can activity D slip before the end date gets extended? c) If activity A slips by one week, how will the slack in activity G be impacted? d) If activity H can somehow be compressed from seven weeks to two weeks, perhaps by adding a significant number of resources, what will be the impact, if any, on the end date of the project? START FINISHExplanation / Answer
a) If I slips by 3 weeks .No impact as K is waiting for H which is taking
3 weeks more than I.
b) D can delyed by 1 week
c) G has total 2 weeks of slack. So if A slips by 1 week, slack of G
will be reduced by 1 week.
d) Currently we need 28 weeks to complete. If H is copresses to 2 weeks.
The requuired weeks will be 24 weeks.