Please help! QUESTION 1 A good change control process will include all of these
ID: 361915 • Letter: P
Question
Please help!
QUESTION 1
A good change control process will include
all of these
a way to formally document change rejection
a way to find out the current status of a change under consideration
a way to formally document change approval
2 points
QUESTION 2
Well-considered and approved changes
may need to be rolled back if conditions change
will never need to be rolled back
can be rolled back easily after work on them has begun
are always costly
2 points
QUESTION 3
Which of the following can be major contributors to project failure? CHECK ALL THAT APPLY
Accepting all changes mentioned by stakeholders
Rejecting all changes suggested by stakeholders
Delays caused by requiring all changes to go through an appropriate change control process
not having a Change Control Board with many stakeholders to provide final approval of all changes
2 points
QUESTION 4
One difference in a project organization where the Project Manager also acts as Business Analyst is that the Project Manager
is only responsible for documenting change requests and their status.
has limited or no ability to evaluate how change requests will impact scope, schedule or budget
has more authority to approve or reject some change requests without consulting the sponsor or Change Control Board
has no authority to approve or reject any change requests without consulting the sponsor or Change Control Board
2 points
QUESTION 5
All of the following should be considered before a change is considered EXCEPT:
Relevance
Risk
Reasonableness
Responsiveness
2 points
QUESTION 6
The purpose of doing a new baseline is
to complete the change approval process
to assess the net impact of a change on the scope, schedule and/or budget for the project
to calculate Earned Value statistics on the project
To document the most up-to-date plans for scope, schedule and budget on the project with all changes applied.
2 points
QUESTION 7
As a project manger your role in potential new project changes is
all of these
receiving and recording change requests from sponsor(s) and/or functional managers
making sure that an appropriate evaluation of all impacts relating to a change request is done
suggesting change requests to sponsor(s) and/or functional mangers
2 points
QUESTION 8
If you are involved in a complex project, and are not receiving change requests or new items to be considered for the sprint backlog, this could be a sign that
You are a fantastic project manager!
You are working on a project that doesn't need to change anything
You are using an Agile methodology
You will be getting changes when your project catches your busy stakeholders attention again.
2 points
QUESTION 9
The purpose of a change log is to
all of these
update plans for the scope, schedule and budget when changes are approved
record only approved change requests
help prevent "zombie changes"
2 points
QUESTION 10
When rejecting a change use the __________________ approach
Just Say No
No, Because
No, But
Yes, But
all of these
a way to formally document change rejection
a way to find out the current status of a change under consideration
a way to formally document change approval
Explanation / Answer
The answers to the given question are below:
1. All of these.
2.May need to be rolled back if conditions changes.
3.Acceping all changes mentioned by stakeholders
Delays caused by requiring all changes to go through an appropriate change control process
Not having a Change Control Board with many stakeholders to provide final approval of all changes
4.Has more authority to approve or reject some change requests without consulting the sponsor or Change Control Board
5.Responsiveness
6.To assess the net impact of a change on the scope, schedule and/or budget for the project
7.All of these.
8.You are using an Agile methodology.
Reason: Agile methodology is a new thing is software that deals with several iterative software development. it has a set of standard methodology which is interactive and solution driven.
9.All of these.
10.Yes, But Aproach.
Reason: because it is more encouraging and doesnt pinned the person down who proposed the change.