Please help! QUESTION 1 A good change control process will include all of these

ID: 361915 • Letter: P

Question

Please help!

QUESTION 1

A good change control process will include

all of these

a way to formally document change rejection

a way to find out the current status of a change under consideration

a way to formally document change approval

2 points   

QUESTION 2

Well-considered and approved changes

may need to be rolled back if conditions change

will never need to be rolled back

can be rolled back easily after work on them has begun

are always costly

2 points   

QUESTION 3

Which of the following can be major contributors to project failure? CHECK ALL THAT APPLY

Accepting all changes mentioned by stakeholders

Rejecting all changes suggested by stakeholders

Delays caused by requiring all changes to go through an appropriate  change control process

not having a Change Control Board with many stakeholders to provide final approval of all changes

2 points   

QUESTION 4

One difference in a project organization where the Project Manager also acts as Business Analyst is that the Project Manager

is only responsible for documenting change requests and their status.

has limited or no ability to evaluate how change requests will impact scope, schedule or budget

has more authority to approve or reject some change requests without consulting the sponsor or Change Control Board

has no authority to approve or reject any change requests without consulting the sponsor or Change Control Board

2 points   

QUESTION 5

All of the following should be considered before a change is considered EXCEPT:

Relevance

Risk

Reasonableness

Responsiveness

2 points   

QUESTION 6

The purpose of doing a new baseline is

to complete the change approval process

to assess the net impact of a change on the scope, schedule and/or budget for the project

to calculate Earned Value statistics on the project

To document the most up-to-date plans for scope, schedule and budget on the project with all changes applied.

2 points   

QUESTION 7

As a project manger your role in potential new project changes is

all of these

receiving and recording change requests from sponsor(s) and/or functional managers

making sure that an appropriate evaluation of all impacts relating to a change request is done

suggesting change requests to sponsor(s) and/or functional mangers

2 points   

QUESTION 8

If you are involved in a complex project, and are not receiving change requests or new items to be considered for the sprint backlog, this could be a sign that

You are a fantastic project manager!

You are working on a project that doesn't need to change anything

You are using an Agile methodology

You will be getting changes when your project catches your busy stakeholders attention again.

2 points   

QUESTION 9

The purpose of a change log is to

all of these

update plans for the scope, schedule and budget when changes are approved

record only approved change requests

help prevent "zombie changes"

2 points   

QUESTION 10

When rejecting a change use the __________________ approach

Just Say No

No, Because

No, But

Yes, But

all of these

a way to formally document change rejection

a way to find out the current status of a change under consideration

a way to formally document change approval

Explanation / Answer

The answers to the given question are below:

1. All of these.

2.May need to be rolled back if conditions changes.

3.Acceping all changes mentioned by stakeholders

Delays caused by requiring all changes to go through an appropriate  change control process

Not having a Change Control Board with many stakeholders to provide final approval of all changes

4.Has more authority to approve or reject some change requests without consulting the sponsor or Change Control Board

5.Responsiveness

6.To assess the net impact of a change on the scope, schedule and/or budget for the project

7.All of these.

8.You are using an Agile methodology.

Reason: Agile methodology is a new thing is software that deals with several iterative software development. it has a set of standard methodology which is interactive and solution driven.

9.All of these.

10.Yes, But Aproach.

Reason: because it is more encouraging and doesnt pinned the person down who proposed the change.