Assignment 7 Resource – 10 pts.                 

Submit your answers to the problems below to Quizzes > Assignments > Assign7 Resource.

UTILIZE the MS Project application and skills learned in previous assignments and exercises to complete this practice exercise on an individual basis. Use Fixed Units (the MS Project default. No need to save/submit MS Project plans.

1.Refer to the activity network table below. Enter this information using MS Project to produce a Gantt chart. Assume that each resource has been assigned to the project activity on a full-time (8 hours/day or 40 hours/week) basis. (5 pts.)

Activity                       Duration                      Predecessors                      Resource Assigned

A. User survey                  4                                  None                           Gail Wilkins

B. Coding                         12                                A                                 Tom Hodges

C. Debug                           5                                  B                                 Wilson Pitts

D. Design interface           6                                  A, C                            Sue Ryan

E. Develop training           5                                  D                                 Reed Taylor

a.What is the project’s Duration?

b.Select the Resource Usage view that identifies the total number of hours and daily commitments of each project team member. What member(s) of the project team is/are overloaded?

A)Duration = 28d, no resources overloaded

B)Duration = 24d, Gail Wilkins overloaded

C)Duration = 32d, no resources overloaded

D)Duration = 32d, Gail Wilkins overloaded

2.Refer to the activity table shown in Problem 1. Suppose that we modified the original table slightly to show the following predecessor relationships between tasks and resources assigned to perform these activities. Modify the plan in Problem 1 and enter this information using MS Project in order to produce a Gantt chart. Assume that each resource has been assigned to the project activity on a full-time basis. (5 pts.)

Activity                        Duration                       Predecessors                    Resource Assigned

A. User survey                  4                                  None                           Gail Wilkins

B. Coding                         12                                A                                 Tom Hodges

C. Debug                           5                                  A                                 Tom Hodges

D. Design interface           6                                  B, C                             Sue Ryan

E. Develop training           5                                  D                                 Reed Taylor

a.What is the project’s Duration?

b.Using the Resource Usage view, determine which member(s) of the project team has/have been overassigned?

c.Click on the Task Usage view to determine the specific days when there is a conflict in the resource assignment schedule. List the resource and the specific days or range(s) of days there is an overload situation.

A)Duration = 24d, no resources overloaded

B)Duration = 27d, Tom Hodges overloaded, during Coding & Debug tasks

C)Duration = 32d, no resources overloaded

D)Duration = 32d, Gail Wilkins overloaded, during Coding & Debug tasks

Explanation / Answer

1. a. project duration is 3 days with the critical path of A-B-C-D-E

b. duartion with 32, no resources are over loaded, hence option C is correct.

2.a. project duration is 27, with critical path of A-B-D-E

b. all the members carries only assigned works and work B allotted more weightage than others

c. option B is correct, Tom Hodges given higher weightage than others