Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Following table calculates and presents expected completion time and standard de

ID: 373414 • Letter: F

Question

Following table calculates and presents expected completion time and standard deviation of each activity :

Activity

Optimistic

Most likely

Pessimistic

Expected time

Standard deviation

A

1.00

4.00

7.00

4.00

1.00

B

3.00

5.00

10.00

5.50

1.17

C

2.00

5.00

8.00

5.00

1.00

D

4.00

6.00

11.00

6.50

1.17

E

1.00

2.00

3.00

2.00

0.33

F

3.00

5.00

7.00

5.00

0.67

G

1.00

2.00

6.00

2.50

0.83

H

2.00

5.00

6.00

4.67

0.67

It is to be noted that :

Expected time = ( Optimistic time + 4 x Most likely time + Pessimistic time)/6

Standard deviation of an activity = ( Pessimistic time – Optimistic time ) / 6

                                                            A

B

C

                                         D

E

                                         F

                                  G

                                                                H

The parallel paths and their cumulative expected durations as follows :

A-C-F-G = 4 + 5 +5 + 2.5 = 16.5

A-D-F-H = 4 + 6.5 + 5 + 4.67 = 20.17

A-D-G-H = 4 + 6.5 + 2.5   + 4.67 = 17.67

B-E-G-H =   5.5 + 2 +    2.5 + 4.67 = 14.67

Out of above, A-D-F-H has the longest duration and hence forms the critical path Duration of the critical path is the expected project completion time. Therefore, expected project completion time will be 20.17 days

CRITICAL PATH = A-D-F-H

EXPECTED PROJECT COMPLETION TIME = 20.17 DAYS

Let Z value corresponding to the probability of completing the project within 22 days = Z1

Variance of duration of critical path

= Sum of variances of A,D,F, and H

= 1^2 + 1.17^2 + 0.67^2 + 0.67^2

= 1 + 1.3689 + 0.4489 + 0.4489

= 3.2667

Standard deviation of critical path

= Square root ( Variance )

= Square root ( 3.2667)

= 1.807

Thus,

Expected duration of critical path + Zvalue x Standard deviation of critical path = 22 days

Or, 20.17 + 1.807.Z1 = 22

Or, 1.807.Z1 = 1.83

Or, Z1 = 1.83/1.807 = 1.0127

Corresponding probability for Z1 =1.0127 ( 1.01 rounded to 2 decimal places) as derived from standard normal distribution table is 0.8437

PROBABILITY OF COMPLETING THE PROJECT WITHIN 22 DAYS = 0.8437

Activity

Optimistic

Most likely

Pessimistic

Expected time

Standard deviation

A

1.00

4.00

7.00

4.00

1.00

B

3.00

5.00

10.00

5.50

1.17

C

2.00

5.00

8.00

5.00

1.00

D

4.00

6.00

11.00

6.50

1.17

E

1.00

2.00

3.00

2.00

0.33

F

3.00

5.00

7.00

5.00

0.67

G

1.00

2.00

6.00

2.50

0.83

H

2.00

5.00

6.00

4.67

0.67

Explanation / Answer

The following represents a project that should be scheduled using CPM IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESSORS a mb 3 5 10 4 6 11 C,D D,E F,G 6 6 b. What is the critical path? A-C-F-H O B-E-G-HH AD-G-H A-D-F-H c. What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time days d. What is the probability of completing this project within 22 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.) Probability