Please answer all sub-parts - Thanks. 2. The project network and activity durati

ID: 378304 • Letter: P

Question

Please answer all sub-parts - Thanks.

2. The project network and activity durations for a maintenance of a computer network, including backups, reformatting the hard drive, etc. are listed below on the activity-on-node network diagram for the project. 3 2 8 2 path? Compute the early and late start schedules. What is the critical path? What is the duration of the critical How much can activity G be delayed without delaying the project? How much can activity B be delayed without delaying the project? Without delaying another activity A. B. C.

Explanation / Answer

Possible parallel paths and their corresponding durations as follows :

A-B-F-J = 2 + 7 + 3 + 5 = 17

A-C-D-F-J = 2 + 8 + 3 + 3 + 5 = 21

A-C-D-H-J = 2 + 8 + 3 + 4 + 5 = 22

A-C-E-H-J = 2 + 8 + 4 + 4 + 5 = 23

A-C-G-H-J = 2 + 8 + 2 + 4 + 5 = 21

Out of above , A-C-D-H-J has the longest duration and hence forms the CRITICAL PATH

CRITICAL PATH IS A-C-D-H-J WITH DURATION 23

The early Start ( ES), Late start ( LS) , Early Finish ( EF), Late Finish ( LF) and Slack for each activity is presented below :

Activity

ES

LS

EF

LF

Slack

A

0

0

2

2

0

B

2

8

9

15

6

C

2

2

10

10

0

D

10

11

13

14

1

E

10

10

14

14

0

F

9

15

12

18

6

G

10

12

12

14

2

H

14

14

18

18

0

J

18

18

23

23

0

ACTIVITY G CAN BE DELAYED BY 2 DAYS WITHOUT DELAYING THE PROJECT

ACTIVITY B CAN BE DELAYED BY 6 DAYS WITHOUT DELAYING THE PROJECT

CRITICAL PATH IS A-C-D-H-J WITH DURATION 23