Please choose the correct answer below. (a) A project can be defined as a set of

ID: 379857 • Letter: P

Question

Please choose the correct answer below.

(a) A project can be defined as a set of large number of activities or jobs (with each activity consuming time & resources) that are performed in a certain sequence determined. • A network is a graphical representation of a project, depicting the flow as well as the sequence of well defined activities & events. • An activity (Also known as task & job) is any portion of a project which consumes time or resources and has definable beginning & ending. • Event (Also known as node & connector) is the beginning & ending points of an activity or a group of activities.

(b) A project can be defined as a set of only a small number of activities or jobs (with each activity consuming time & resources) that are performed in a certain sequence determined. • A network is a graphical representation of a project, depicting the flow as well as the sequence of loosely defined activities & events. • An activity (Also known as task & job) is any portion of a project which consumes time or resources and has definable beginning & ending. • Event (Also known as node & connector) is the beginning & ending points of an activity or a group of activities.

(c) A project can be defined as a set of only a small number of activities or jobs (with each activity consuming time & resources) that are performed in a certain sequence determined. • A network is a graphical representation of a project, depicting the flow as well as the sequence of loosely defined activities & events. • An activity (Also known as task & job) is any portion of a project which consumes time or resources and has definable beginning & ending. • Event (Also known as node & connector) is the beginning,dummy & ending points of an activity or a group of activities.

(a) A project can be defined as a set of large number of activities or jobs (with each activity consuming time & resources) that are performed in a certain sequence determined. • A network is a graphical representation of a project, depicting the flow as well as the sequence of well defined activities & events. • An activity (Also known as task & job) is any portion of a project which consumes time or resources and has definable beginning & ending. • Event (Also known as node & connector) is the beginning & ending points of an activity or a group of activities.

(b) A project can be defined as a set of only a small number of activities or jobs (with each activity consuming time & resources) that are performed in a certain sequence determi
ned. • A network is a graphical representation of a project, depicting the flow as well as the sequence of loosely defined activities & events. • An activity (Also known as task & job) is any portion of a project which consumes time or resources and has definable beginning & ending. • Event (Also known as node & connector) is the beginning & ending points of an activity or a group of activities.

(c) A project can be defined as a set of only a small number of activities or jobs (with each activity consuming time & resources) that are performed in a certain sequence determined. • A network is a graphical representation of a project, depicting the flow as well as the sequence of loosely defined activities & events. • An activity (Also known as task & job) is any portion of a project which consumes time or resources and has definable beginning & ending. • Event (Also known as node & connector) is the beginning,dummy & ending points of an activity or a group of activities.

Explanation / Answer

4. A project consists of large number of activities. Network depicts the flow of the project. Activity is time and resource bound. Event is the milestone.