In your final project, you will revise and compile each part of the final projec

ID: 3824721 • Letter: I

Question

In your final project, you will revise and compile each part of the final project that you have been working on. Submit your final Portfolio Project with the following components:

Project preparation and project charter (Remember you’re your project charter will not be graded again.)

Project scope management plan and WBS

Communication management plan

Project risk and change management plans

Quality management plan

Project closure plan.

In addition, also include the following elements:

An executive summary that offers a high-level description of the project you have developed.

A conclusion that includes a self-assessment as a project manager assigned to this IT project. Address key elements you identified in throughout the project, and identify additional areas that you think have benefitted you and contributed to the success of your project.

Explanation / Answer

     Introduction
    Purpose
    Purpose of the project
Emergency Response System is to be the only system that in event of emergency or crisis, the airlines to efficiently manage execution of the entire crisis management activity. This application enables the airlines to initiate crisis, notify concerned staff, follow-up availability with the support team at the operation area, provide ready reference of data to support inquiries from NOK (Next of Kin) of PDA (Persons Directly Affected), regular updates PDA’s (passenger or crew or others) status and aligns PDAs with NOKs, update cargo status, generate reports and facilitates stand-down of the crisis.
    Purpose of the document
The purpose of the document is to capture the business requirements of Emergency Response System. This document ensures the envisaged requirements are comprehended well by Indigo project team, TCG Digital solution architects, developers and quality assurance team and other related stakeholders to accurately transform the business requirements into system requirements, design and code.

    Document Conventions
The document categorizes the high level scope in functional modules and each module is elaborated individually. The overall business flow diagram provides a link across all the functional modules. The legends for BPM notification are explained in section 7 of the document.

    Intended Audience
The intended audience for this document are:
    Business users
    Solution Architects
    Developers
    Operation Support Group
    Testing team

    Project Scope
Following are the list of functional modules and their corresponding availability over different devices:

Functional Modules    Web    Mobile and Tablet
(iOS & Android only)
Emergency Initiation Management      
Emergency Notification Management      
Data feed Management      
Call Center Management      
Demand Management         (with offline data sync)
Checklist Management         (with offline data sync)
Emergency Stand-down      
Peace time management      
User Management      
Login Authentication and Authorization       
Message broadcasting         (with offline data sync)

    Scope Exclusions
    Success Criteria
    Project Success Criteria
As part of the formal process to transition from development into production stakeholders must be satisfied that the business requirements are appropriately addressed.
    UAT Success Criteria
Based on the UAT Test cases (to be provided by IndiGo), following severity matrix and priority matrix are to be maintained for Go-live.
UAT Bug Severity     Defect Count    Severity Description
Severity 1    0    System aborts without a business workaround. This is normally associated with system crashes that make the system unusable. The system or an entire business function is down or inoperable and it prevents further execution
Severity 2    0    System does not adhere to the requirements; serious errors in results or the performance is substantially degraded. But business workaround exists
Severity 3    0 – 10     These types of defects are generally tolerable or deferrable, such as errors in format of displays or printouts
Severity 4    0 – 15     An improvement suggestion, which is not a defect and does not prevent the system from functioning

UAT Bug Priority     Defect Count    Priority Description
Priority 1    0    Blocker, critical or showstopper defects. Entire functionality is blocked or a feature is unusable with no workaround, no testing can proceed as a result of this.
Priority 2    0    Main feature or functionality is incorrect and does not adhere to the requirements, but workaround is available, performance issues, regression issues, environmental issues and important UI errors related to branding.
Priority 3    0 – 5     Minor functionality is incorrect but workaround is available, cosmetic errors not related to branding.
Priority 4    0 – 10     Minor cosmetic errors, improvement suggestions which does not impact the functionality in any way.
Abbreviation    Description

ERS    Emergency Response System
PDA    Passenger Directly Affected
PNL    Passenger Name List
NOK    Next Of Kin
IP    Interested Party
ERM    Emergency Response Management
SMS    Short Messaging Services
SPOC    Single Point Of Contact
AMOS    Aircraft Maintenance Operations Simulation
AIMS    Airplane Information Management System
OCC    Operation Control Center
HRMS    Human Resource Management System
ESB    Enterprise Service Bus
AOCS    Airport Operation and Customer Service
    Other Notes

    Role Hierarchy
The ERS system will be having a role hierarchy of 2 levels as follows:
Level    Role Name    Role description
Level 1    Super Admin    This role will be having all the controlling privileges of the ERS system. The two departments that will be specifically mapped to this role are ERM and ERC.
Level 2    ERS Users    All other departments, who will be accessing the ERS system, for example: In-flight Services, Call Center, Flight Safety etc., will be categorized under this role.

    Department Hierarchy
The ERS system will be having a department hierarchy of 2 levels as follows:
Level    Hierarchy Name    Description
Level 1    Department    The parent department, for example OCC. When demands from one department are assigned to other departments, only the department name will be visible.
Level 2    Sub-department    Parent departments may or may not have sub-departments. For example, for OCC as parent department, sub-departments can be Dispatchers, Logistics etc.,


    Functionality Access mapping
Following are the different functional activities which will be made configurable for access rights modification for different departments created.

Module    Functionality
Emergency Initiation Management    Emergency Initiation
Emergency Notification Management    Select departments & initiate notify
Data feed Management    Excel upload for persons directly affected
     Excel upload for cargo directly affected
     Excel upload for crew directly affected
     Excel upload for flight schedule
     Excel upload for on-board IndiGo passengers
     Excel upload for flight maintenance records
     Excel upload for flight weight and balance records
     Excel upload for support member training records
     Verify passenger manifest
     Verify cargo manifest
Call Center Management    Search for affected persons and cargo items
     Update caller details
     View activity details against a ticket number
     Update activity details against a ticket number
     Fine tune messages that can be communicated to NOKs
Media Management    View media queries
     Publish press release
     Publish President’s message
Demand Management    View department specific demands
     Raise department specific demands
     Approve demands that require approval
Checklist Management    View and update own-department specific checklists
     View sub-department (of own department) checklists
Emergency Stand-down    Submit own-department specific closure reports
     Close or terminate emergency
Peace time management    Update own-department specific checklist
     Update all department’s checklist
     Update master data for departments
     Update master data for functionality access mapping
     Update master data for emergency types
     Update master data for demand types
     Update master data for event specific notification template
     Open archived incidents for attachment uploads
     Upload own-department specific lessons learnt
     Upload all department’s lesson learnt
     Upload incident specific reports for archived incidents
     Close archived incidents for attachment uploads
User Management    Activate support members and assign roles
Login Authentication and Authorization    Unlock user account
  
      
    Appendix A: Assumptions and Dependencies
    Assumptions
    Appendix B: Business Risks

None identified at this stage of the project.     Introduction
    Purpose
    Purpose of the project
Emergency Response System is to be the only system that in event of emergency or crisis, the airlines to efficiently manage execution of the entire crisis management activity. This application enables the airlines to initiate crisis, notify concerned staff, follow-up availability with the support team at the operation area, provide ready reference of data to support inquiries from NOK (Next of Kin) of PDA (Persons Directly Affected), regular updates PDA’s (passenger or crew or others) status and aligns PDAs with NOKs, update cargo status, generate reports and facilitates stand-down of the crisis.
    Purpose of the document
The purpose of the document is to capture the business requirements of Emergency Response System. This document ensures the envisaged requirements are comprehended well by Indigo project team, TCG Digital solution architects, developers and quality assurance team and other related stakeholders to accurately transform the business requirements into system requirements, design and code.

    Document Conventions
The document categorizes the high level scope in functional modules and each module is elaborated individually. The overall business flow diagram provides a link across all the functional modules. The legends for BPM notification are explained in section 7 of the document.

    Intended Audience
The intended audience for this document are:
    Business users
    Solution Architects
    Developers
    Operation Support Group
    Testing team

    Project Scope
Following are the list of functional modules and their corresponding availability over different devices:

Functional Modules    Web    Mobile and Tablet
(iOS & Android only)
Emergency Initiation Management      
Emergency Notification Management      
Data feed Management      
Call Center Management      
Demand Management         (with offline data sync)
Checklist Management         (with offline data sync)
Emergency Stand-down      
Peace time management      
User Management      
Login Authentication and Authorization       
Message broadcasting         (with offline data sync)

    UAT Success Criteria
Based on the UAT Test cases (to be provided by IndiGo), following severity matrix and priority matrix are to be maintained for Go-live.
UAT Bug Severity     Defect Count    Severity Description
Severity 1    0    System aborts without a business workaround. This is normally associated with system crashes that make the system unusable. The system or an entire business function is down or inoperable and it prevents further execution
Severity 2    0    System does not adhere to the requirements; serious errors in results or the performance is substantially degraded. But business workaround exists
Severity 3    0 – 10     These types of defects are generally tolerable or deferrable, such as errors in format of displays or printouts
Severity 4    0 – 15     An improvement suggestion, which is not a defect and does not prevent the system from functioning

UAT Bug Priority     Defect Count    Priority Description
Priority 1    0    Blocker, critical or showstopper defects. Entire functionality is blocked or a feature is unusable with no workaround, no testing can proceed as a result of this.
Priority 2    0    Main feature or functionality is incorrect and does not adhere to the requirements, but workaround is available, performance issues, regression issues, environmental issues and important UI errors related to branding.
Priority 3    0 – 5     Minor functionality is incorrect but workaround is available, cosmetic errors not related to branding.
Priority 4    0 – 10     Minor cosmetic errors, improvement suggestions which does not impact the functionality in any way.

     Overall Business Flow Diagram


    Nonfunctional Requirements
ERS    Emergency Response System

PDA    Passenger Directly Affected
PNL    Passenger Name List
NOK    Next Of Kin
IP    Interested Party
ERM    Emergency Response Management
SMS    Short Messaging Services
SPOC    Single Point Of Contact
AMOS    Aircraft Maintenance Operations Simulation
AIMS    Airplane Information Management System
OCC    Operation Control center
HRMS    Human Resource Management System
ESB    Enterprise Service Bus
AOCS    Airport Operation and Customer Service

    Symbols used in business flow diagrams
Symbol    Meaning        Symbol    Meaning
     The control will wait at this point till the time all other activities are complete.              From this point, only one activity will get activated based on respective conditions.
     From this point, all of the subsequent activities will simultaneously start.               Intermediate task within a process flow, which may or may not impact the main business flow.
     The control will not wait for all the activities to complete. Common task is initiated for any of the activities.              Sub task. The detailed of that task or functional module is explained in other section of the document.
     From this point, any one of the activity or all of the activities can start simultaneously.              Conditional activity. If the condition is not met, then the subsequently associated task will be skipped.


   Appendix B: Business Risks
None identified at this stage of the project.