Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Please Help Marlyn Hart, operations manager at Hart Electronics, faces assembly-

ID: 392754 • Letter: P

Question

Please Help

Marlyn Hart, operations manager at Hart Electronics, faces assembly-Ine balancing prob ems. She hasbeen told that the firm needs to complete 1,400 elactronic relays par day. Thera are 420 minures of productve time n each working day (which is equalant to 25,200 seconds). Th assemblytine actties are gvan below Must Follow Must Fallow Task Time (seconds Task Task Time (seconds) Task F, G 12 15 C. K Using longest task (operating) tme heuristic, group the assembly-ine activities into appropriate workstations. Complete the folowing table. H, I,J The actuel efficiency of the balance is % enter your response rounded" one decin s' place.

Explanation / Answer

a) Given,

Demand = 1400 units / day = 1400 units/25200 sec day

Average throughput rate = 25200/1400 = 18 sec

So, cycle rate = 18 sec

Minimum number of workstations= sum of total task times / cycle time

                                = (13+4+9+11+6+12+5+6+7+5+4+15)/18 = 97/18 = 5.38 workstations = 6 workstations

b) Task Table

Task

Task time

Precedence

A

13

-

B

4

A

C

9

B

D

11

-

E

6

D

F

12

E

G

5

E

H

6

F,G

I

7

H

J

5

H

K

4

I,J

L

15

C,K

The total station time is nothing but the cycle time. So, total station time of each station is 18 sec

In order of longest task time, tasks: L>A>F>D>C>I>E>H>G>J>B>K

Workstation 1:

                                First task =A (As L is dependent on C)

                                Time left= 18-13= 5 sec

                                Second task =B

                                Time left= 5-4= 1 sec                     

So, workstation 1: A->B

Workstation 2:

                                First task =D

                                Time left= 18-11 = 7 sec

                                Second task =E

                                Time left= 7-6 = 1 sec

So, workstation 2: D->E

Workstation 3:

                                First task =F

                                Time left= 18-12 = 6 sec

                                Second task =G

                                Time left= 6-5 = 1 sec

So, workstation 3: F->G

Workstation 4:

                                First task =C

                                Time left= 18-9 = 9 sec

                                Second task =H

                                Time left= 9-6 = 3 sec

So, workstation 4: C->H

Workstation 5:

                                First task =I

                                Time left= 18-7 = 11 sec

                                Second task =J

                                Time left= 11-5= 6 sec

                                Third task =K

                                Time left= 6-4= 2 sec

So, workstation 5: I->J->K

Workstation 6:

                                First task =L

                                Time left= 18-15 = 3 sec

So, workstation 6: L

Work Station

Tasks

Workstation Time

Idle Time

1

A->B

17 sec

1 sec

2

D->E

17 sec

1 sec

3

F->G

17 sec

1 sec

4

C->H

15 sec

3 sec

5

I->J->K

16 sec

2 sec

6

L

15 sec

3 sec

Were you able to assign all the tasks to the theoretical minimum no of workstations: Yes

Total idle time = 1+1+1+3+2+3= 11 sec

Efficiency with 6 workstations = (sum of all tasks) / (no of workstations *   Cycle time)

        = (97)/ (6*18) = 0.898 or 89.8 %

Task

Task time

Precedence

A

13

-

B

4

A

C

9

B

D

11

-

E

6

D

F

12

E

G

5

E

H

6

F,G

I

7

H

J

5

H

K

4

I,J

L

15

C,K