Part 1 (Textbook Questions) 50 points Data from Chapter Exercise Questions 2 and

ID: 417618 • Letter: P

Question

Part 1 (Textbook Questions) 50 points

Data from Chapter Exercise Questions 2 and 3 from CPM 3e Chapter 9 are provided below.

Question 2

Activity

Immediate
Predecessor

Duration in days (unconstrained at 8-hours per day)

Resource

Hourly cost

Available
Work Hours per Day (constrained)

A

Evaluate freezers

2

Alcides

$45

6

B

Chart temperatures

6

Joan

$50

4

C

Review service record

2

Alcides

D

Consult with HVAC engineer

A,B,C

3

Alcides

E

Develop construction plan

D

10

Joan

F

Complete IC assignment

E

2

Alcides

G

Complete ROI analysis

E

5

Joan

H

Conduct regulatory review

E

4

Joan

I

Obtain construction approval

F,G,H

2

Alcides

Question 3

WBS

Activity

Immediate
Predecessor

Duration in weeks
(unconstrained at
8-hours per day)

Resource

Hourly cost

Available
Hours per
Week (constrained)

1

Operational definition

1.1

Research literature

3

Becky

$35

30

1.2

Identify and define terms

1.1

1

Ann

$60

30

1.3

Obtain approval of definition

1.2

2

Clive

$50

20

2

Target Selection

2.1

Solicit partners for pilot

2

Ann

2.2

Hold brainstorming meeting

2.1

2

Becky

2.3

Identify characteristics of targets

2.2, 3.1

1

Ann

2.4

Obtain approval of partners

2.3, 1.2, 3.4

1

Clive

3

Question set

3.1

Identify process group members

2

Clive

3.2

Develop question set

2.3

4

Ann

3.3

Prototype and validate question set

3.2

3

Becky

3.4

Add partners

3.1, 2.1

3

Becky

4

Pilot process

4.1

Schedule with target audience

2.4

2

Becky

4.2

Conduct beta test

3.4, 2.4

2

Clive

4.3

Process feedback from target audience

4.2

2

Ann

4.4

Conduct pilot

4.3

2

Clive

4.5

Analyze results

4.4

2

Clive

Respond to the following questions:

Determine the unconstrained critical path and its length (use days for Question 2, use weeks for question 3; use project days only, no weekends).

Determine the total hours and the hours per person required to complete the work?

Determine the total labor cost and the labor cost per person?

Prepare a Gantt chart illustrating the project length using constrained resource assignments and illustrating logical precedence diagramming for each activity (e.g., show finish-start relationships). Include color-coding by resource for each bar of the Gantt chart.

Develop a responsibility histogram for each resource over the length of the project and describe what adjustments, if any, were made to the project schedule to effectively deal with resource overloads or other schedule conflicts related to precedence (logic) requirements

Prepare a resourced-constrained (yet resource-leveled) critical path and its length.

Prepare a figure similar to Exhibit 9.9 (CPM) illustrating a cumulative cost curve.

Activity

Immediate
Predecessor

Duration in days (unconstrained at 8-hours per day)

Resource

Hourly cost

Available
Work Hours per Day (constrained)

A

Evaluate freezers

2

Alcides

$45

6

B

Chart temperatures

6

Joan

$50

4

C

Review service record

2

Alcides

D

Consult with HVAC engineer

A,B,C

3

Alcides

E

Develop construction plan

D

10

Joan

F

Complete IC assignment

E

2

Alcides

G

Complete ROI analysis

E

5

Joan

H

Conduct regulatory review

E

4

Joan

I

Obtain construction approval

F,G,H

2

Alcides

Explanation / Answer

Q.2.

Critical Path - B-D-E-G-I and it takes 26 days.

b. Total hours and the hours per person required to complete the work-

Duration - (2+6+2+3+10+5+2+4+2) * 8 = 288 total hours

Hours of Alcides = (2+2+3+2+2) * 8 = 88 hours required to complete the work

Hours of Joan = (6+10+5+4) * 8 = 200 hours required to complete the work

c. Total labor cost and the labor cost per person

Total labor cost = (88 * 45) + (200 * 50) = $13,960

Labor cost of Alcides = 88 * 45 = $3,960

Labor cost of Joan = 200 * 50 = $10,000

Activity Duration ES LS EF LF Total Float Free Float Successor Critical activity A 2 0 4 2 6 4 4 D B 6 0 0 6 6 0 0 D Critical C 2 0 4 2 6 4 4 D D 3 6 6 9 9 0 0 E Critical E 10 9 9 19 19 0 0 F,G,H Critical F 2 19 22 21 24 3 3 I G 5 19 19 24 24 0 0 I Critical H 4 19 20 23 24 1 1 I I 2 24 24 26 26 0 0 Critical