Problem 11-20 Prepare a master schedule given this information: It is now the en

ID: 427277 • Letter: P

Question

Problem 11-20

Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. (Leave no cells blank - be certain to enter "0" wherever required.)

June July 1 2 3 4 5 6 7 8 Forecast 30 30 30 30 40 40 40 40 Customer orders (committed) 33 25 16 11 8 3 Projected on-hand inventory MPS ATP

Explanation / Answer

Period

2

3

4

5

6

7

8

9

Forecasted Sales

30

30

30

30

40

40

40

40

Customer Orders

33

25

16

11

8

3

0

0

Projected on Hand (64)

34

4

44

14

44

4

34

64

ATP

97

9

58

33

76

41

74

104

Master Production Schedule

0

0

70

0

70

0

70

70

Period

2

3

4

5

6

7

8

9

Forecasted Sales

30

30

30

30

40

40

40

40

Customer Orders

33

25

16

11

8

3

0

0

Projected on Hand (64)

34

4

44

14

44

4

34

64

ATP

97

9

58

33

76

41

74

104

Master Production Schedule

0

0

70

0

70

0

70

70