Question

Consider the end-item weekly MRPs for May 1 with Qd missing in each MRP. Match the correct MRP with the proper lot size discipline.

MRP A

MRP B

MRP C

MRP D

Question 2. For Qd=4, which MRP is correct?

(A) MRP A (B) MRP B (C) MRP C (D) MRP D (E) none of the above

Question 3. For Qd=9+, which MRP is correct?

(A) MRP A (B) MRP B (C) MRP C (D) MRP D (E) none of the above

Question 4. For Qd=LFL, which MRP is correct? Q=4

(A) MRP A (B) MRP B (C) MRP C (D) MRP D (E) none of the above

5-1 5-8 5-15 5-22 5-29 GR 340 156 10 14 SR 80 LT=2 PSB 442 182 26 16 11 SS=8 POR 9 Qd=?

Explanation / Answer

Q2 = MRP B

Q3 = MRP A

Q4 = MRP C

Explanation: The answer depends upon the planned order release (POR) and the closing inventory (PSB) on 5-29. POR quantity will be recieved 2 weeks later (LEadtime = 2 weeks ) and will be added to PSB

For Qd = 4, POR has to be in multiplpes of 4.

For Qd = 9+, POR has to be equal to or more than 9

For Qd = LFL, POR has to be the minimum possible to meet the demand and safety stock requirement.