Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Part 1. The jobs A,B,C,D,E, arrived in that order to be processed on two machine

ID: 467588 • Letter: P

Question

Part 1.

The jobs A,B,C,D,E, arrived in that order to be processed on two machines.

Job

A

B

C

D

E

Time on Machine 1

35

41

49

28

53

Time on Machine 2

32

56

36

48

55

How many of the statements are correct?

     (A) 0     (B) 1     (C) 2     (D) 3     (E) 4

Statement 1. In the FIFO schedule, the total time of completion is 271.

Statement 2. In the FIFO schedule, the flow time of job D is 216.

Statement 3. In the FIFO schedule, the total queue time of job C is 76.

Statement 4. In the FIFO schedule, the total idle time of machine 2 is 35.

Part 4. Questions 6-7

An organization that continuously processes proposals is addressing a large backlog due to an historical FIFO sequencing rule. You have been asked to determine a schedule that minimizes the processing time of project proposals through the editing department and revision department. The editing department identifies changes and the revision department incorporates the changes and produces a final proposal document for release. A proposal must pass through each department. Each department has personnel to service only one document at a time. The editing time is dependent on the type of proposal and the revision time is dependent on the size of the proposal. The time estimates below have been provided to you for scheduling.

Question 6. What is the minimum processing time in minutes?

     (A) 525   (B) 1025   (C) 522   (D) 502   (E) none of the above

Question 7. What is the minimum average jobs per minute that can be achieved?

     (A) 281   (B) 21   (C) 41   (D) 13   (E) none of the above

Proposal #

Editing Time (minutes)

Revision Time (minutes)

1

17

18

2

24

26

3

18

17

4

13

15

5

24

23

6

28

26

7

20

21

8

22

20

9

16

17

10

12

10

11

21

22

12

30

28

13

18

19

14

20

19

15

12

13

16

25

27

17

22

25

18

23

21

19

17

16

20

26

29

21

14

16

22

19

18

23

29

27

24

16

15

25

26

25

Question 8. Using the aggregate run-out method for the assembly line schedule problem below, what is the production for product C in hours?

     (A) 3     (B) 4     (C) 6     (D) 28     (E) None of the above

Available production = 53 hours.

Product

Line

Production

Inventory

Demand

Products

Hours/Item

Items

Items/week

A

0.1

120

50

B

0.2

100

80

C

0.1

110

50

D

0.3

200

80

E

0.2

90

40

Job

A

B

C

D

E

Time on Machine 1

35

41

49

28

53

Time on Machine 2

32

56

36

48

55

Explanation / Answer

Part 1:.

Scheduling done as per FIFO method:

Job

Time on Machine 1

Time on Machine 2

Machine 1 Start

Machine 1 Finish

Machine 2 Start

Machine 2 Finish

Machine 2 Idle

Job Idle time

A

35

32

0

35

35

67

35

0

B

41

56

35

76

76

132

9

0

C

49

36

76

125

132

168

0

7

D

28

48

125

153

168

216

0

15

E

53

55

153

206

216

271

0

10

The last job E finishes at 271 period on Machine 2. The total time of completion = 271, Statement 1 is correct.

The Job D finish time of Machine 2 is 216, thus, the flow time of Job D = 216, Statement 2 is correct.

The Job C has to wait till period 76 to start processing on machine 1, thus, total queue time of job C = 76, Statement 3 is correct.

Total idle time on Machine 2 = 35 + 9 = 44 periods, the us the statement 4 is incorrect.

Thus, only three statements are correct.

Correct Option: (D) 3

Part 2:

For reducing the idle time for N jobs scheduling on two workstations Johnson’s Rule is applied.

Steps for Johnson’s Rule

For “n” jobs on two machines, the steps to follow for Johnson’s rules are:

Repeat steps 1, 2, and 3 until all jobs have been scheduled.

For example, process time of proposal#10 is minimum 10 at the WS#2, thus, sequence the Proposal#10 in last. Remove that proposal from the list. Again the minimum processing time of 12 minutes is for Proposal#15 at WS#1, thus, sequence Proposal#15 first.

WS#1

WS#2

Sequence

Proposal #

Editing Time (minutes)

Revision Time (minutes)

WS#1 Start Time

WS#1 Finish time

WS#2 Start

WS#2 finish time

1

15

12

13

0

12

12

25

2

4

13

15

12

25

25

40

3

21

14

16

25

39

40

56

4

9

16

17

39

55

56

73

5

1

17

18

55

72

73

91

6

13

18

19

72

90

91

110

7

7

20

21

90

110

110

131

8

11

21

22

110

131

131

153

9

17

22

25

131

153

153

178

10

2

24

26

153

177

178

204

11

16

25

27

177

202

204

231

12

20

26

29

202

228

231

260

13

12

30

28

228

258

260

288

14

23

29

27

258

287

288

315

15

6

28

26

287

315

315

341

16

25

26

25

315

341

341

366

17

5

24

23

341

365

366

389

18

18

23

21

365

388

389

410

19

8

22

20

388

410

410

430

20

14

20

19

410

430

430

449

21

22

19

18

430

449

449

467

22

3

18

17

449

467

467

484

23

19

17

16

467

484

484

500

24

24

16

15

484

500

500

515

25

10

12

10

500

512

515

525

Question 6. What is the minimum processing time in minutes?

     (A) 525   (B) 1025   (C) 522   (D) 502   (E) none of the above

Minimum processing time for all the proposal in WS#2 is 525 minutes.

Correct Option: (A)

Question 7. What is the minimum average jobs per minute that can be achieved?

     (A) 281   (B) 21   (C) 41   (D) 13   (E) none of the above

Minimum Average job per minute = no. of Jobs/minimum total processing time = 25/525 = 0.05

Correct Option: (E)

Question #8:

Aggregate Run-out Method attempts to use the total production capacity available to produce just enough of each product so that if all production stops, inventory of each product runs out at the same time.

Aggregate Run-out time in months

   = Total Inventory and Machine hours Available/Machine Hours required

Aggregate ROT = (53 + 121)/58 = 3 weeks

1

2

3

4=1x2

5=1*3

6=ROTx3

7=3+6

8=7-2

9=1x8

Product Line

Production

Inventory

Demand

Inventory

Demand

week Desired ending inve,

Weeks desired End Inv + Forecast

Req. Prod.

Assembly time Allocated

Products

Hours/Item

Items

Items/week

Hours

Hours

Items

units

Hours

A

0.1

120

50

12

5

150

200

80

8

B

0.2

100

80

20

16

240

320

220

44

C

0.1

110

50

11

5

150

200

90

9

D

0.3

200

80

60

24

240

320

120

36

E

0.2

90

40

18

8

120

160

70

14

121

58

111

Thus, processing time reuired for product C = 9 hours.

Correct Option: (E)

Job

Time on Machine 1

Time on Machine 2

Machine 1 Start

Machine 1 Finish

Machine 2 Start

Machine 2 Finish

Machine 2 Idle

Job Idle time

A

35

32

0

35

35

67

35

0

B

41

56

35

76

76

132

9

0

C

49

36

76

125

132

168

0

7

D

28

48

125

153

168

216

0

15

E

53

55

153

206

216

271

0

10