Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Complete the following aggregate plan for January through April using the Chase

ID: 469652 • Letter: C

Question

Complete the following aggregate plan for January through April using the Chase Strategy. Additional Information: Inventory holding cost = $10 per unit per month, Hiring cost = $50 per unit, Firing cost = $100 per unit, December Production = 230 units Basic Production Cost = $10 per unit Period

Forecast Prior Production Inventory # hire units # fire units Extra Cost December ----- 20 ----- ----- J

anuary 350 February 300 March 280 April 460 Complete the following aggregate plan for January through April using the Chase Strategy. Additional Information: Inventory holding cost = $10 per unit per month, Hiring cost = $50 per unit, Firing cost = $100 per unit, Basic Production Cost = $10 per unit December Production 200 units

Period              Forecast     Prior Production Inventory     hire unts       fire units extra cost

December                                                        20

January 350

February 300

March 280

April 460

Explanation / Answer

Inventory holding cost = $10 per unit per month

Hiring cost = $50 per unit

Firing cost = $100 per unit

December Production = 230 units

Basic Production Cost = $10 per unit Period

Extra cost = Hiring cost x hire units + Firing cost x fire units

Period

Forecast

Prior Production

Inventory

Actual Production

hire units

Fire units

Extra Cost

Prod. Cost

Total Cost

December

20

January

350

200

0

330

130

0

$6500

$3300

$9800

February

300

330

0

300

0

30

$3000

$3000

$6000

March

280

300

0

280

0

20

$2000

$2800

$4800

April

460

280

0

460

180

0

$9000

$4600

$13600

Total Cost of Case plan = Total (Hiring + Firing + Production) costs

Total Cost of plan = $9,800 + $6,000 + $4,800 + $13,600 = $34,200

Total Cost of chase plan = $34,200

Period

Forecast

Prior Production

Inventory

Actual Production

hire units

Fire units

Extra Cost

Prod. Cost

Total Cost

December

20

January

350

200

0

330

130

0

$6500

$3300

$9800

February

300

330

0

300

0

30

$3000

$3000

$6000

March

280

300

0

280

0

20

$2000

$2800

$4800

April

460

280

0

460

180

0

$9000

$4600

$13600