There are three activities in making a print circuit board: etching, plating, an

ID: 472610 • Letter: T

Question

There are three activities in making a print circuit board: etching, plating, and laminating. They need to be done in sequence. Each activity is done by one machine attended by one operator. The first activity takes 10 minutes, the second activity takes 6 minutes and the third activity takes 8 minutes. The hourly wage for the operators is $15. What is the labor cost of each finished board? There are three activities in making a print circuit board: etching, plating, and laminating. They need to be done in sequence. Each activity is done by one machine attended by one operator. The first activity takes 10 minutes, the second activity takes 6 minutes and the third activity takes 8 minutes. The hourly wage for the operators is $15. What is the labor cost of each finished board? There are three activities in making a print circuit board: etching, plating, and laminating. They need to be done in sequence. Each activity is done by one machine attended by one operator. The first activity takes 10 minutes, the second activity takes 6 minutes and the third activity takes 8 minutes. The hourly wage for the operators is $15. What is the labor cost of each finished board? There are three activities in making a print circuit board: etching, plating, and laminating. They need to be done in sequence. Each activity is done by one machine attended by one operator. The first activity takes 10 minutes, the second activity takes 6 minutes and the third activity takes 8 minutes. The hourly wage for the operators is $15. What is the labor cost of each finished board?

Explanation / Answer

Hourly wage = $15

Per minute wage = 15 / 60 = $0.25 per minute

Minutes taken for producing one board = 10 + 6 + 8 = 24 minutes

Labour cost per finished board = 24 x 0.25 = $6