Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 5.70 Please show complete solution procedure, and include cash flow diag

ID: 1765974 • Letter: P

Question

Problem 5.70

Please show complete solution procedure, and include cash flow diagrams for each machine.

The following costs are associated with three tomato-peeling machines being considered for use in a canning plant. If the canning company uses an interest rate of 12%, which is the best alternative? Use NPW to make your decision. (Note: Consider the least common multiple as the study period.)

Machine                          A                         B                         C

First cost                        $52,000                $63,000              $67,000

O&M costs                     $15,000                $9,000                $12,000

Annual benefit                $38,000                $31,000              $37,000

Salvage value                 $13,000                $19,000              $22,000

Useful life (yrs)                4                           6                         12

Explanation / Answer

The least common multiple life is 12 years, so this will be used as the analysis period.

Machine A

NPW4 = -$52,000 + ($38,000 - $15,000)(P/A, 12%, 4) + $13,000(P/F, 12%, 4)

           = -$52,000 + $69,851 + $8,262

           = $26,113

NPW12= NPW4 [1 + (P/F, 12%, 4) + (P/F, 12%, 8)]

           = $26,113 [1 + (1.12)-4 + (1.12)-8]

         = $53,255

Machine B

NPW6 = -$63,000 + ($31,000 - $9,000)(P/A, 12%, 6) + $19,000(P/F, 12%, 6)

           = -$63,000 + $90,442 + $9,625

           = $37,067

NPW12 = NPW6 [1 + (P/F, 12%, 6)]

            = $37,067 [1 + (1.12)-6]

            = $55,846

Machine C

NPW12 =-$67,000+($37,000 - $12,000)(P/A, 12%, 12)+$22,000(P/F, 12%, 12)

             = -$67,000 + $154,850 + $5,647

             = $93,497

Machine C is the correct choice