CM306 Fundamentals of Scheduling Float and Lag Quiz 3 A B C D The following is a
ID: 1885308 • Letter: C
Question
CM306 Fundamentals of Scheduling Float and Lag Quiz 3 A B C D The following is a: Finish to start relationship with a 5 day lag Finish to finish relationship with a 5 day lag Start to start relationship with a 5 day lag Start to finish relationship with a 5 day lag 14 9 23 4 A B C D The following is a: Finish to start relationship with a 8 day lag Finish to finish relationship with a 8 day lag Start to start relationship with a 8 day lag Start to finish relationship with a 8 day lag 14 12 5 A B C D The following is a: Finish to start relationship with a 3 day lag Finish to finish relationship with a 3 day lag Start to start relationship with a 3 day lag Start to finish relationship with a 3 day lagExplanation / Answer
3. A FINISH TO START RELATIONSHIP WITH A LAG OF 5 DAYS (as seen clearly in the diagram relationship is Finish to start because second activity starts when first activity finishes )
4. C start to start relationship with a 8 day lag (because both activity starts simultaneously )
5. A. FINISH TO START RELATIONSHIP WITH A LAG OF 3 DAYS