Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Mayes & Co. is currently evaluating two mutually exclusive investments. After do

ID: 2633738 • Letter: M

Question

Mayes & Co. is currently evaluating two mutually exclusive investments. After doing a scenario analysis and applying probabilities to each scenario, it has determined that the investments have the following distribution around the expected NPVs.

Probability

NPV(A)

NPV(B)

10%

$ (30,600.00)

$ (11,475.00)

20%

$   (7,650.00)

$     1,913.00

40%

$   15,300.00

$   15,300.00

20%

$   38,250.00

$   28,688.00

10%

$   61,200.00

$   42,075.00

You were asked to determine which of the two projects should be accepted.

Bonus:

Please show detailed steps and use Excel!!!!! WILL offer max points

Probability

NPV(A)

NPV(B)

10%

$ (30,600.00)

$ (11,475.00)

20%

$   (7,650.00)

$     1,913.00

40%

$   15,300.00

$   15,300.00

20%

$   38,250.00

$   28,688.00

10%

$   61,200.00

$   42,075.00

Explanation / Answer

1.

2)

Variance of A:$144,199,440.00

Variance of B = $215,070,187.56

3) From above table

4) coefficient of variation = std deviation/expecetd NPV

coefficient of variation of A = 12,008.31/$15,300.00= 0.78

coefficient of variation of A = 14,665.27/15,300.20= 0.96

Bonus:

1.

probability of a negative NPV for A = 10%+20%= 30%

probability of a negative NPV for B = 10%

2.Project A should be accepted because it has comparable expected NPV but lower risk

Probability NPV(A) NPV(B) Probability*NPV(A) Probability*NPV(B) 10% ($30,600.00) ($11,475.00) ($3,060.00) ($1,147.50) 20% -7,650.00 1,913.00 ($1,530.00) $382.60 40% 15,300.00 15,300.00 $6,120.00 $6,120.00 20% 38,250.00 28,688.00 $7,650.00 $5,737.60 10% 61,200.00 42,075.00 $6,120.00 $4,207.50 Expected NPV $15,300.00 $15,300.20