Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider the following two mutually exclusive projects Whichever project you cho

ID: 2778704 • Letter: C

Question

Consider the following two mutually exclusive projects Whichever project you choose if any you require a 15 percent return on your investment. What is the discounted payback period for each project? (Do not round Intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) If you apply the discounted payback criterion which investment will you choose? What Is the NPV for each project? (Do not round Intermediate calculations and round your answers to 2 decimal places, e.g.. 32.16.) If you apply the NPV criterion which investment will you choose? What Is the IRR for each project? (Do not round Intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g.. 32.16.) If you apply the IRR criterion which investment will you choose? What is the profitably index for each project? (Do not round Intermediate calculations and round your answers to 3 decimal places, e.g.. 32.161.) If you apply the profitability Index criterion which Investment will you choose? Based on your answers in (a) through (e). which project will you finally choose?

Explanation / Answer

The required table is as below

Year

15% factor

Project A

Project B

NCF

PV of NCF

NPV

NCF

PV of NCF

NPV

0

1

-344,000

-344,000

-344,000

-49,000

-49,000

-49,000

1

0.8696

51,000

44,349.6

-299,650.4

24,600

21,392.16

-27,607.84

2

0.7561

71,000

53,683.1

-245,967.3

22,600

17,087.86

-10,519.98

3

0.6575

71,000

46,682.5

-199,284.8

20,100

13,215.75

2,695.77

4

0.5718

446,000

255,022.8

55,738.0

15,200

8,691.36

11,387.13

b-1.

Discounted payback period:

Project A: 3 years + a fraction of the 4th year

                 = 3 years + (199,284.8 / 255,022.8)

                 = 3.78 years

Project B: 2 years + a fraction of the 3rd year

                 = 2 years + (10,519.98 / 13,215.75)

                 = 2.80 years

b-2.

Based on discounted payback period project B should be chosen, since it has smaller recovery period.

c-1.

NPV of Project A = $55,738

NPV of project B = $11,387.13

c-2.

Based on NPV project A should be chosen, since it has greater returns.

Year

15% factor

Project A

Project B

NCF

PV of NCF

NPV

NCF

PV of NCF

NPV

0

1

-344,000

-344,000

-344,000

-49,000

-49,000

-49,000

1

0.8696

51,000

44,349.6

-299,650.4

24,600

21,392.16

-27,607.84

2

0.7561

71,000

53,683.1

-245,967.3

22,600

17,087.86

-10,519.98

3

0.6575

71,000

46,682.5

-199,284.8

20,100

13,215.75

2,695.77

4

0.5718

446,000

255,022.8

55,738.0

15,200

8,691.36

11,387.13