For the following Time estimates: Fill in the Expected Time and the Variances th
ID: 3173659 • Letter: F
Question
For the following Time estimates: Fill in the Expected Time and the Variances that have been left blank: The standard deviation of the Critical Path, if this path consists of Activities A, H, G. and I is If the expected completion time for a given Critical Path is 47 days, with a standard deviation of 4 days. The probability of completing the project within 51 days is the probability of completing the project within 53 days is How many days should be allocated for a 99.942% probability of completing the project?Explanation / Answer
Q.2 (a) Data is correctedly filled in the blank spaces
(b) Summation of variances of A, H, G and I= 1 + 0.44 +0.44 + 1.36 = 3.24
standerd deviation = 1.8
Q.3 is specifically askedhere so i am answering it here
Expected Critical time = 47 days and standered deviation = 4days
(a) P( X <= 51 ; 47; 4) so Z -value = 51- 47 / 4 = 1
so for Z value = 1 relative probabilbility from Z table = 0.8413
so P( X <= 51 ; 47; 4) = 0.8413; Here you have written 68% but that is the probabilty of P ( 43 < =X<=51; 47; 4) for vales mean +- sigma
(b) P ( X< = 53; 47; 4) here z value = 1.5
so P ( X< = 53; 47; 4) = 0.9332
(c) given is P (x < =X; 47;4) = 0.99942
so z value for that probability from Z table = 3.262
so number of days given = 47 + 3.262 * 4 = 60 days