Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider the following time series data. Week 1 2 3 4 5 6 Value 18 12 16 11 18 1

ID: 3209363 • Letter: C

Question

Consider the following time series data.

Week

1

2

3

4

5

6

Value

18

12

16

11

18

13

Using the naïve method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy.

(a)

Mean absolute error

If required, round your answer to one decimal place.

(b)

Mean squared error

If required, round your answer to one decimal place.

(c)

Mean absolute percentage error

If required, round your intermediate calculations and final answer to two decimal places.

(d)

What is the forecast for week 7?

Week

1

2

3

4

5

6

Value

18

12

16

11

18

13

Explanation / Answer

as naive method provide most recent value should be forecast of next month.

hence

a) from above Mean absolute error =5.4

b)Mean squared error =30.2

c)Mean absolute percentage error=0.3956*100=39.56%

d)forecast for 7th weeek =13

c)

Week Value(A) forecast(F) |A-F| (A-F)^2 |A-F|/A 1 18 2 12 18 6 36 0.50 3 16 12 4 16 0.25 4 11 16 5 25 0.45 5 18 11 7 49 0.39 6 13 18 5 25 0.38 13 Total 27 151 1.978 mean =T/5 5.4 30.2 0.3956