Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Reliable Garage is completing production of the J2000 kit car. The following dat

ID: 333283 • Letter: R

Question

Reliable Garage is completing production of the J2000 kit car. The following data are available for the? project:

????????????????????????????????????????????????????????????????????????????????????????????????????????  

Activity

?(dayday?s)

Immediate? Predecessor(s)

A

55

minus?

B

77

A

C

22

B

D

1010

C

E

44

C

F

44

C

G

33

F

H

44

?D, E, G

The critical path is A-B-C-D-H and the project duration is 28 day?(s).

?(Enter your response as a whole? number.)

c. What is the slack for each? activity?

Activity

Activity

Time

?(dayday?s)

Slack

?(dayday?s)

A

55

nothing

B

77

nothing

C

22

nothing

D

1010

nothing

E

44

nothing

F

44

nothing

G

33

nothing

H

44

nothing

Activity

Activity Time

?(dayday?s)

Immediate? Predecessor(s)

A

55

minus?

B

77

A

C

22

B

D

1010

C

E

44

C

F

44

C

G

33

F

H

44

?D, E, G

Explanation / Answer

Dur EF= ES+Dur LF-EF Activity Pre Duration ES EF Critical LS LF Slack A 5 0 5 Yes 0 5 0 B A 7 5 12 Yes 5 12 0 C B 2 12 14 Yes 12 14 0 D C 10 14 24 Yes 14 24 0 E C 4 14 18 20 24 6 F C 4 14 18 21 25 7 G F 3 18 21 25 28 7 H ?D, E, G 4 24 28 Yes 24 28 0 Critical A-B-C-D-H Project duration 28