Please find below table which describes expected completion time for each activi

ID: 372891 • Letter: P

Question

Please find below table which describes expected completion time for each activity:

Activity

Optimistic

Most likely

Pessimistic

Expected time

A

4

7

10

7

B

3

8

10

7.50

C

4

6

8

6.00

D

2

4

5

3.83

E

3

6

10

6.17

Following may be noted :

Expected time = ( Optimistic time + 4 x Most Likely time + Pessimistic time) / 6

The parallel activity paths and their corresponding durations as follows :

Start -A- C- Finish = 7 + 6 = 13 days

Start – B – E – Finish = 7.5 + 6.17 = 13.67 days

Start – A – D -E – Finish = 7 + 3.83 + 6.17 = 17 days

Since Start-A-D-E-Finish has the longest duration, it forms the critical path . Duration of the critical path is same as project completion time . Therefore, expected completion time is 17 days

EXPECTED COMPLETION TIME = 17 DAYS

Activity

Optimistic

Most likely

Pessimistic

Expected time

A

4

7

10

7

B

3

8

10

7.50

C

4

6

8

6.00

D

2

4

5

3.83

E

3

6

10

6.17

Explanation / Answer

Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table

The expected completion time is ___ days (Respone as an integer)

Activity Optimistic Most likely Pessimistic A 4 7 10 B 3 8 10 C 4 6 8 D 2 4 5 E 3 6 10 Start Finish