Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Maxwell Software, Inc., has the following mutually exclusive projects Year Proje

ID: 2731631 • Letter: M

Question

Maxwell Software, Inc., has the following mutually exclusive projects Year Project A ProjectEB -$29,000 16,000 10,000 11,500 -$26.000 15,000 11,500 3,500 0 a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Payback period Project A Project B years years a-2. Which, if either, of these projects should be chosen? Project A Project B O Both projects Neither project b-1. What is the NPV for each project if the appropriate discount rate is 13 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) NPV Project A Project B b-2. Which, if either, of these projects should be chosen if the appropriate discount rate is 13 percent? Project A Project B O Both projects O Neither project

Explanation / Answer

Project A Project B Year Project A Cumulative Cash flow Project B Cumulative Cash flow 0                              (26,000)         (26,000)          (29,000)        (29,000) 1                                15,000         (11,000)            16,000        (13,000) 2                                11,500                  500            10,000           (3,000) 3                                   3,500              4,000            11,500             8,500 1. Project Payback Period Payback Period Years Project A 1 years + 11000/11500 1.96 Project B 2 years + 3000/11500 2.26 2. Project to be chosen :- Project B should be chosen although it has higher payback period, but it has more Cash generation then Project A 3. NPV at Discount Rate @ 13% Project A Project B Year Project A PVF@ 13% Present Value Cumulative Cash flow Project B PVF@ 13% Present Value Cumulative Cash flow 0                              (26,000)              1.000           -26,000        (26,000)    (29,000)         1.000     -29,000    (29,000) 1                                15,000              0.885            13,274        (12,726)      16,000         0.885      14,159    (14,841) 2                                11,500              0.783               9,006           (1,226)      10,000         0.783         7,831      (4,841) 3                                   3,500              0.693               2,426             2,274      11,500         0.693         7,970         6,659 NPV Project A = 2274 NPV Project B = 6659 4. Project to be chosen on the basis of NPV Project B should be chosen as it has higher NPV.