Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Maxwell Software, Inc., has the following mutually exclusive projects Year Proje

ID: 2731737 • Letter: M

Question

Maxwell Software, Inc., has the following mutually exclusive projects

Year Project A Project B

0 -$23,000 -$26,000

1 13,500 14,500

2 10,000 11,000

3 3,200 10,000

a-1. Calculate the payback period for each project.

Payback period

Project A years

Project B years

a-2. Which, if either, of these projects should be chosen? 1. Project A 2. Project B 3. Both Projects 4. Neither project

b-1. What is the NPV for each project if the appropriate discount rate is 17 percent?

NPV

Project A $

Project B $

b-2. Which, if either, of these projects should be chosen if the appropriate discount rate is 17 percent? 1. Project A 2. Project B 3. Both projects 4. Neither project

Explanation / Answer

Part a-1)

To compute payback period, we first need to prepare cumulative cash flow table

Project A

Year

CF

CCF

0

-23000

-23000

1

13500

-9500

2

10000

500

3

3200

3700

Payback period = last year of negative ccf + last negative ccf/ cf in first year of positive ccf

                                = 2 + 9500/ 10000

                                = 2.95 years

Project B

Year

CF

CCF

0

-26000

-26000

1

14500

-11500

2

11000

-500

3

10000

9500

Payback period = last year of negative ccf + last negative ccf/ cf in first year of positive ccf

                                = 3 + 500/ 10000

                                = 3.05 years

Part a-2

Project A should be selected as it has lower payback period.

Part b-1

To compute NPV, we need to discount all the cash flows, and add the Present values.

Project A

Year

CF

PV factor 17%

Pv

0

-23000

1

-23000.00

1

13500

0.854701

11538.46

2

10000

0.730514

7305.14

3

3200

0.624371

1997.99

NPV

-2158.42

So NPV is -2158.42

Project B

Year

CF

PV factor 17%

Pv

0

-26000

1

-26000.00

1

14500

0.854701

12393.16

2

11000

0.730514

8035.65

3

10000

0.624371

6243.71

NPV

672.52

Part b-2

Since NPV of project B is greater, Project B should be selected.

Year

CF

CCF

0

-23000

-23000

1

13500

-9500

2

10000

500

3

3200

3700