The diagram below shows an activity network of a project, in which the duration

ID: 3809011 • Letter: T

Question

The diagram below shows an activity network of a project, in which the duration is in days. Use the Critical Path Scheduling Algorithm to find a schedule for three workers. How many days does the project take to complete by your schedule? days Does this produce an optimum schedule? ('Y' for 'yes'. 'N' for 'No.') Use the Critical Path Scheduling Algorithm to find a schedule for two workers. How many days does the project take to complete by your schedule? days Does this produce an optimum schedule? ('Y' for 'yes'. 'N' for 'No.')

Explanation / Answer

1)

There are many path to complete the activity like

start - A-D-F-K-Finish will take (0+1+3+2+2)= 8 days

start-B-F-K-Finish will take (3+2+2)= 7 days

start c-e-g -H-K-Finish = 0+1+4+2+1+2 =10 days

start-c-E-G-J-finish = 1+4+2+1 = 8 days

2)

YES it will produce an optimal solution

example

START - B - F - K - Finish = 3+2+2 = 7 days

this is optimal solution

3)

CRitical path is the longest path to complete

start C-E-G -H-K-Finish = 0+1+4+2+1+2 =10 days

4)

It is not optimal path