Hey All, Its a project crashing question. Can someone help me showing how did LS

ID: 3816508 • Letter: H

Question

Hey All, Its a project crashing question. Can someone help me showing how did LS 7 (in activity E) came from in the diagram? I thought EF = is 11 and - 5 activity so LS would be 6. So I am so confused where did LS 7 (in activity E) came from? I dont know to how to fine due date crashing. I would really apprecite it if someone can help me out in this please with explanation I dont need answer without explanation becuase I have the answer. I want to understand how you came to the answer. Thanks a ton.This is the question and you can also find it at the bottom of screen shot.

If the due date to finish the project is 10 weeks, crash the project to meet the due date.

t Activity EFT ES LS LF 6 12 C 22 6 12 Start 6 4 6 6 11 7| 12 4 Find the critical path the longest path through the network. Way 1: A- D 4 6 10 Way 2: A C D 4 2 6 12 Way 3: A- C- E- Way- 4: B- C- D- Way 5: B C- E 3 2 5- 10 The longest way through the network is A C D- 12 If the due date to finish the project is 10 weeks, crash the project to meet the due date. Find the duration of each activity, the critical path and the cost of crashing the activities after crashing the project to due date. FINISH

Explanation / Answer

Start the project by getting the values from start as Early start(ES) to Early Finish(EF).

Now start discussion about Late Start(LS) and Late Finish(LF). As shown in Example, Our Project completed at 12 weeks. Thus, Late Finish uses Backward Pass to reach at each node.